Weekly Marine Update

Progress Update for July 7, 2017

 Skagerrak

Halden Load out Skagerrak Vessel

Completed cable installation..

 Polar King

Polar King (2)

Completed trenching activity.

Rock Piper

Rockpiper

Loaded one load of rock and will commence subsea rock installation in the Cape Ray area.



Progress Report 


Activity Estimated Duration
Schedule
Grappling

Completed
April 18 - April 19, 2017 &
April 22 - 23, 2017
Pre-Lay Survey

Completed
April 19 - April 23, 2017
Cable #1 Pull-in - Cape Ray, NL

Completed
April 26
Cable #1 Laying

Completed
April 27 - May 13, 2017
Cable #1 Pull-in - Point Aconi, NS

Completed
May 14, 2017
Cable #2 Transpooling

Completed
May 16 - May 30, 2017
Cable #2 Pull-in - Cape Ray, NL

Completed
May 31, 2017
 Cable #2 Laying

Complete
May 31 - June 12, 2017
 Cable #2 Pull-in - Point Aconi, NS

Complete
June 12 - June 16, 2017
Cable West Work

Completed
 June 17 –June 28, 2017
Cable trenching

Completed
April 27 - June 29, 2017
Berming where required
4 - 8 weeks
July 7 - September 1, 2017
Installation Complete
  September 1, 2017

 