Weekly Marine Update

Progress Update for May 19, 2017

 Skagerrak

Halden Load out Skagerrak Vessel

Currently at Atlantic Canada Bulk Terminal in Sydney, NS undergoing transpooling. Expected completion of transpooling is June 2, 2017.

 Polar King

Polar King (2)

At 7 a.m. the Polar King was at kilometre post 152 and the Capjet is trenching from kilometre post 147 to kilometre post 153. Over the next 24 hours the Capjet will continue trenching from kilometer post 153 to kilometre post 163.


 
Activity Estimated Duration
Schedule
Grappling

Completed
April 18 - April 19, 2017 &
April 22 - 23, 2017
Pre-Lay Survey

Completed
April 19 - April 23, 2017
Cable #1 Pull-in - Cape Ray, NL

Completed
April 26
Cable #1 Laying

Completed
April 27 - May 13, 2017
Cable #1 Pull-in - Point Aconi, NS

Completed
May 14, 2017
Cable #2 Transpooling
17 days
May 15 - June 2, 2017
Cable #2 Pull-in - Cape Ray, NL
1 - 2 days
June 2, 2017
 Cable #2 Laying
 10 days
June 2 - June 12, 2017
 Cable #2 Pull-in - Point Aconi, NS
1 - 2 days
June 13 - June 14, 2017
Cable trenching
Up to 70 - 85 days
April 27 - July 11, 2017
Berming where required
Up to 17- 30 days
July 6 - August 4, 2017
Installation Complete
  September 1, 2017

 